Project Description

Background

Toray Resin has been a VASEY service and project customer since 2011.

Problem

A serious equipment failure occurred the day before Good Friday. Since Toray Resin’s chiller is on the production line, operating round-the-clock, downtime for repair or installation is never an option. Two out of the three compressors on the chiller were not functioning – a major problem since it was an essential component to their 24/7 operation. The new chiller had to be up and running by Sunday (Easter) night.

Solution

Since Toray Resin had previously scheduled a shutdown during the Good Friday/Easter holiday weekend, it was the perfect time for VASEY to replace the chiller.

End Result

VASEY flawlessly coordinated all the moving parts for a seamless installation. The moment the switch was turned off for the Easter weekend VASEY began work. VASEY had the project completed, up and running by Saturday – midday – more than 24-hours ahead of schedule. The plant manager was thrilled as he could now spend Easter Sunday with his family rather than working all day at the facility.

Review Case Study

Download Now (PDF Format)